How to Estimate a Story Without Final Design: Size the Work Before the Mockups Are Done

Name the design state, write one assumption and agree a re-vote trigger so your number still means something when mockups change.

Estimation Cleiton Loiola · · 6 min read

The story's on the board and the designer has dropped a link to the mockups in chat. Then someone adds, "Heads up, these are still a draft." Your team's task is to estimate story without final design: a checkout page whose screens might change next week. A few people vote anyway, a few reach for the question-mark card, and nobody's sure what the number will mean once the design moves.

Waiting on another team is a different problem. When a vendor or partner team holds you up, you can focus on sizing the work you control while something outside the team is pending. With unfinished design, the uncertain scope sits inside your own story, and it shifts every time a new version of the mockups lands.

I'd suggest a short routine you run before anyone votes. Name the design state you're sizing, write one assumption, and agree what change triggers a re-vote. It's built from ordinary planning poker habits and hasn't been tested as a formal method, so shape it to fit your team.

Why unfinished design splits the vote

When votes on a design-dependent story scatter, people are usually picturing different screens. Take that checkout page. The engineer looked at last week's sketch, saw a form with a few fields and voted 3. The tester opened the newer draft, which adds a loading state, a declined-card message and a saved-address option, and voted 8.

Both votes make sense for what each person saw, because they sized two different versions of the page. The split tells you the room hasn't agreed on scope yet, and you want to know that before anything gets written down.

The risk is voting before anyone notices the gap. TeamRetro's guide to running planning poker says, "A vote taken before the room understands the story isn’t an estimate; it’s a guess with a number attached." With a design in progress, understanding the story includes knowing which version of the screens you're talking about. If half the room has seen the draft and the other half only saw the sketch, whatever number you record is that guess.

And averaging won't rescue it. Calling the checkout story a 5 because the votes were 3 and 8 hides the fact that nobody agreed on what's being built. Whoever opens the story next will find a number with no sign of which design it was sized against.

Name the design state to estimate story without final design

Before the first vote, ask the designer which state the design is in. If they aren't at refinement, the product owner can usually answer. Three labels cover most cases:

  • Sketch: rough layout and flow, with little or no visual detail.
  • Draft: screens exist and most of the flow is drawn, but details may still change.
  • Final: the designer doesn't expect changes before the team builds it.

Write the label on the story itself so it stays with the estimate. A 5 on a sketch and a 5 on a final design say different things, and the label is how anyone reading later can tell them apart.

Then say out loud what that state doesn't show yet. Drafts often skip empty states (what a screen shows when there's no data), error states and responsive layouts for smaller screens. If those aren't drawn, decide now whether they belong to this story or a later one.

A three-line card on the story keeps all of this short. For the checkout example it might read:

Design state: draft

In scope: payment form, loading state, declined-card message

Not yet shown: empty cart, mobile layout, saved addresses

None of this is new to planning poker. Mountain Goat Software's description of the technique includes a step before anyone picks a card: "The team clarifies assumptions and what must be true for the item to be considered complete." For stories you can't size yet, it says, "If the item cannot be estimated because too much is unknown, record the question that needs answering."

That can happen with design. Maybe the flow isn't settled, or the designer is still choosing between two layouts. Write the open question on the story, agree who'll answer it, and send the story back to refinement, or run a spike (a short, time-boxed piece of investigation) if the open part is technical. For a wider set of things to check first, use the questions to ask before you play a card on an unclear story.

Write one assumption and a re-vote trigger

Once the state is named, write down the one assumption your vote rests on. For a design-dependent story it's usually about reuse, something like "uses existing components, no new interaction patterns." Pick the assumption that would move the number most if it turned out wrong.

Why only one? A list of six assumptions doesn't get read, and nobody rechecks it when the design changes. One sentence fits on the story and people remember it. If your team already keeps estimate notes that record why you chose the number, the assumption goes there, next to the design state.

Agree the re-vote trigger too, still before anyone votes. It's the design change that would make the current number wrong, and good triggers are concrete enough that anyone on the team can spot them:

  • A new screen appears in the flow.
  • The design needs a component your library doesn't have yet.
  • The flow changes, for example an added step or a different order.

Copy edits, colour tweaks and spacing changes don't count. Say that out loud as well, so nobody reopens the estimate every time a button moves a few pixels.

Then put the whole thing in one sentence on the story. For the checkout page: "We're voting on the draft. We assume existing components and no new interaction patterns. We re-vote if a new screen or a new component appears." Anyone who picks up the story later can check the current mockups against that sentence in under a minute.

Re-votes need a limit, or a moving design turns into a weekly estimation meeting. When a trigger fires, re-vote once with the new state named. If the room still won't settle after discussion, TeamRetro says "the story isn’t estimable yet" and you should split it or send it back for refinement "rather than voting a third time and hoping."

With design work, a split often follows the line between what's drawn and what isn't. Build the payment form now and leave saved addresses for a story that waits on final screens. For the full set of options, see when to re-vote, split or park a user story after the reveal.

Run the round with designers in the room

Whenever a story depends on the designer's work, invite them to refinement. TeamRetro says, "Bring the whole delivery team, not just engineering. QA and design see effort a ticket description doesn’t mention." A designer knows the draft is still missing two error states, and a tester knows each of those states needs checking. A one-line ticket shows neither.

The round itself is standard planning poker, as Mountain Goat Software describes it: "Each estimator chooses a card privately. Everyone reveals at the same time. If the estimates differ, the team talks about the differences and estimates again." Its list of who can take part includes designers, along with "anyone else whose work is needed to get the product backlog item done." It also says, "Do not treat disagreement as a problem to remove. Treat it as information."

Whether designers also vote is your team's call, and neither source settles it. If design work is part of what done means for this story, a designer's card belongs in the round. If they're there to answer questions about the design state, they can skip the vote and still shape the conversation. But agree which it is before the round starts, so nobody feels left out halfway through.

When the cards split, hear the highest and lowest voters first. On a design story, ask each of them which version of the screens they pictured. That one question usually shows whether you're looking at a scope gap or a difference in effort.

A facilitator can run the whole reveal in five lines:

  1. "We're sizing the checkout page at the draft state. Empty cart and mobile layouts aren't in this story."
  2. "Our assumption is existing components and no new interaction patterns."
  3. "Pick your card privately, and we'll all reveal together."
  4. "Highest and lowest, tell us what you pictured."
  5. "Let's re-vote once or accept the number. If it still splits, we split the story or send it back."

If your team estimates online, TinyTroop is free online planning poker. The facilitator shares one link, and a designer can join with just a display name and no account. Votes stay secret until the reveal, and when they split, the outliers get named so you know whom to hear first.

Try the routine on your next design story

Before your next refinement, pick one story with a draft design and fill in the three-line card with your designer. Add the sentence with the assumption and the trigger, then vote and listen to how the conversation goes after the reveal.

While the mockups are still moving, a number only means something next to the design state and the assumption it was sized against. Write those two things down, and when the screens change, your team knows whether the estimate still applies.