How to Estimate a Story That Depends on Another Team or Vendor

A three-question routine for sizing the work you control and handling the wait you don't, before the cards go down.

Estimation Cleiton Loiola · · 6 min read

You're in refinement, and the next story is a checkout change that needs a new payment API from another team. Someone asks whether the API will be ready. Nobody knows. You vote anyway, and the cards come back anywhere from 3 to 21.

That spread has little to do with the checkout code. Some people sized the work, and some sized the wait. There's a short routine to estimate a story with an external dependency: estimate the work your team controls, write down the wait you don't control as a named assumption, and park the story if nobody has committed to a date.

Why dependent stories break estimates

Any team that shares a product with other teams will run into dependencies. Trouble starts when one goes unnamed until the cards are already on the table.

The tricky ones sit outside your team. The Scrum Alliance article on managing dependencies describes teams that need "assistance or support from a) another scrum team, b) another department, or c) an external vendor." Your checkout story is the first case. A story waiting on your platform department or on a vendor's sandbox is the second or third.

Vote on that kind of story without talking about the dependency, and people tend to split into two camps. Some pad: AgileSeekers' guide to team dependencies lists "Teams pad estimates to protect themselves" among the results of ignoring dependencies. Others commit on hope. They vote small and assume the API turns up on time.

A single vote asks people to mix two different things. Story points size your team's effort and how complex the work is. But waiting in someone else's queue isn't effort, and it doesn't shrink when your team gets faster. When one card has to carry both, the reveal gives you a spread of guesses about another team's calendar.

Split the story into ours and theirs

Start before anyone picks a card, with one question to the room: what do we need from anyone else to finish this story? The answer usually cuts the story in two. "Ours" is the work your team does and controls. "Theirs" is whatever has to arrive from outside before the story can be done.

For the checkout story, ours might be the new screen, the error handling, tests against a stub of the payment API, and the release. Theirs is the API from the payments team. Write both down and you can see which part the vote is about.

Theirs goes down as a request with a name and a date on it, such as a card authorization endpoint from the payments team in the test environment, needed by day five of the sprint. Kendis's dependency management guide gives a rule of thumb: "every dependency needs an owner, a needed-by date and a status. Without those three it is a hope." A request with no owner and no date is exactly that.

Status is the part teams skip. Kendis says, "A dependency is only real when the giving team has it in their plan." The status that counts is accepted. And having sent them a message doesn't qualify. The Scrum Alliance article makes the same push: "Ask for delivery commitments from external contributors. Get specific dates and delivery expectations."

For any story that touches another team or a vendor, run a three-question check before the vote:

  1. What do we control?
  2. What do we wait for?
  3. Who owns the wait, and by when?

The first answer is what you'll estimate. The second and third become the assumption you log.

One more thing belongs in ours: the time someone spends chasing the other team. Scrum Alliance says, "Ensure that the hours required for dependency oversight are subtracted from the developer’s sprint capacity." Following up and checking whether the API has landed is work your team does, so count it.

Vote on the part you control

Say the scope of the vote out loud first. If each person holds a different picture of the story, the cards can't agree. A short script does it: "We're voting on our work only. The payments API is assumption A1." Write A1 on the story so it stays visible while you talk.

Keep every vote hidden until everyone has picked. If someone says "that's an 8 at least, their API is a mess" before the round, the room anchors on it and you're back to estimating the wait. In TinyTroop, which is free online planning poker for agile teams, votes stay secret until the reveal, and when the votes split it names the outlier votes so you know whom to hear first. Physical cards work too, as long as everyone flips at once.

On a split, start with the outliers. With a dependent story, a 13 among a row of 3s often means that person still has part of the wait in their number. Maybe they expect to build a workaround if the API is late, or they know the payments team's test environment breaks a lot. Hearing the outlier votes first takes a couple of minutes and usually shows you which assumption differs.

It works the other way too. A 2 among a row of 5s can mean someone assumed the API already exists and only counted the wiring. Ask them what they pictured before you ask anyone to change their card.

AgileSeekers suggests a refinement question that fits this moment: "Has this dependency been confirmed or just assumed?" If the outlier's extra work belongs to your team, such as a fallback or a mock, add it to ours. If it's waiting, move it into the assumption.

I'd re-vote once and then move on.

If the second round still splits, either the team doesn't yet agree on what ours contains or the dependency is bigger than it looked. More cards won't settle either one, so take the story to the next decision.

Log the dependency or park the story

Once you have a number for your part, decide what happens to the wait. It comes down to one question: has the other party committed to a date?

What you have from the other party What to do with the story
A committed date that fits your sprint Keep it. Log the dependency as a visible assumption with owner, needed-by date and status.
A date requested, no answer yet Cut scope to the part you can finish alone, or park it until they reply.
No answer, or nobody has asked Park it. The product owner takes the conversation to the other team or vendor.

The middle row is the tempting one. A date you've asked for feels close to a date someone promised, and the story looks ready. Treat it as no date until the other team says yes.

A visible assumption lives on the story, where anyone can read it. For example: "A1: card authorization endpoint from the payments team. Owner: their team lead. Needed by day five. Status: accepted." AgileSeekers says managing dependencies is about "making them visible, negotiable, and intentionally planned." If the date slips mid-sprint, everyone knows which story is at risk and why.

For an unconfirmed dependency, AgileSeekers says, "If a dependency cannot be confirmed, teams should reduce scope or move the story out of the sprint." Cutting scope works when ours can ship something useful alone, like the checkout screen behind a feature flag, tested against the stub. If it can't, park the story.

Scrum Alliance says, "do not bring a PBI into the sprint if there’s an external dependency without an associated commitment of delivery." A PBI is a product backlog item, the Scrum term for any entry on the backlog, stories included. You can still refine and estimate a story with an open dependency, but it shouldn't enter the sprint yet.

Chasing that commitment is the product owner's job. Another department's priorities or a vendor's contract are business questions, and the product owner has the standing to raise them. The team's part is to hand over a precise request: what you need, from whom, and by when.

When you park, move the story down your story list and note on it what it's waiting for. Bring it back when the other party answers, and don't vote on it again until then. The post on when to re-vote, split or park a user story covers the rest of the minutes after a reveal.

A rule you can use in the room tomorrow

Vote on ours, log theirs, park the unconfirmed. Say that line at the start of the next story that touches another team, and let the three-question check do the sorting.

It works best before sprint planning. AgileSeekers says, "Strong teams treat dependency identification as a standard backlog refinement activity, not a last-minute sprint planning surprise." Add the three questions to your refinement agenda and dependencies show up earlier, while you can still ask for a date.

Your retrospective closes the loop. Look at the dependencies you logged during the sprint and ask whether each team or vendor delivered what they said, when they said. If one keeps slipping, ask them for dates sooner, or stop pulling stories that depend on them into a sprint without a firm commitment.

At your next refinement, take the first story that's blocked on someone else and run the three questions before anyone votes.

Keep one thing on the card, the work your team controls, and put the wait on the story with an owner and a date. Got a blocked story coming up? Start a free room and run the check before the first card goes down.