How to Estimate Unplanned Work in Planning Poker When Support Keeps Interrupting
Set interrupt capacity from recent sprints first, then use the vote to size only the planned stories.
Pick someone to throw at
You're halfway through sprint planning when someone mentions the payments alert that fired twice last week. Suddenly every estimate creeps up. One engineer plays a 5, another plays a 13 "because support will eat half the week," and the talk drifts away from the story on the screen.
If your team carries production support or an on-call rotation, you've probably tried to estimate unplanned work in planning poker. The fix starts before anyone picks a card. As a team, set aside interrupt capacity based on what recent sprints showed and keep that work out of the story vote. Then the round only has to size the planned stories.
Why you can't estimate unplanned work in planning poker
A story card assumes you know roughly what the work is and that it'll start when you choose. Interrupts break both assumptions. Nobody knows what next Tuesday's incident will involve, or whether there'll be one at all.
That worry is fair. Mary Iqbal writes on Scrum.org that for many organizations, production support is unpredictable and can't be delayed until the next sprint. Those requests have to be handled right away, so the work will come whether your plan has room for it or not.
Production support and on-call duty are the usual culprits. The pattern's the same for any work that shows up without warning, like a security patch or an urgent data fix for a customer.
Teams tend to respond in one of two ways, and neither helps the round. Some smuggle support into the story estimates. A 3 becomes a 5 "just in case," and a few weeks later nobody can say which part of the 5 was the story. Others ignore interrupts, fill the sprint to the brim and miss the goal when the first alert lands.
Both habits make the vote noisy. When each person adds a private guess about support, the cards split for reasons that have nothing to do with the story, and you end up debating pager load in the middle of a conversation about a checkout form.
Decide the interrupt capacity from recent sprints
Set the reserve before the first card is played. Iqbal describes an option where Developers estimate during Sprint Planning how much unplanned work to expect and leave some capacity free to deal with it. To size that space, she asks two questions: "What percentage of the Scrum Team’s time during previous Sprints was eaten up by unplanned work? Is the unexpected work highly variable, or is it fairly steady?"
Those questions point you at your own history, which is the best data you've got. Before your next planning session, look back at the last three sprints and list every incident and every "quick question" that took an afternoon. For each sprint, write down roughly what share of the team's time that work used, then agree on one number or a narrow range for the next sprint. And add a note to check it at the retrospective.
How you read those numbers depends on their shape. Numbers that sit close together mean a stable pattern, and you can pick a single figure. If one sprint got hammered and the next was calm, pick a range and plan your stories against the top end of it.
Agilemania's Naveen Kumar Singh says to reserve a small percentage of the team's capacity for unexpected tasks during sprint planning, and to keep that buffer flexible enough for varying levels of unplanned work. He writes, "This doesn’t mean reducing the team's capacity but rather acknowledging that unplanned work is a reality and accounting for it."
Neither source gives a figure for how big the reserve should be, and that's fine, because your last three sprints already reflect your on-call rotation and your customers in a way a borrowed rule of thumb can't.
Agree the reserve as a whole team. The Developers know how support felt from the inside, and the Product Owner needs to see how much room is left for backlog work. Once both have signed off on the number, nobody has to defend it story by story.
If your team works in flow without sprints, the idea carries over. Keep part of your capacity, such as a work-in-progress slot or an expedite lane, open for interrupts, and check its size at your regular review.
Sort the work: reserve, card or split
Some support-flavored work belongs in the reserve, and some of it deserves a card. Agilemania says that categorizing unplanned work helps the team assess its impact and decide how to handle it without compromising the sprint's objectives. For most teams, the useful buckets are urgent bugs, customer requests that can't wait, and technical problems such as a failing job or a struggling server.
At refinement, run any item that came from support through three questions:
- Is it planned?
- Does it have a known scope?
- Can it wait until next sprint?
Two or more "no" answers send it to the reserve. If the item is planned, scoped and can wait, it's a story, and it gets a card like everything else. The check sits well next to the questions to ask before you play a card when a story is fuzzy for other reasons.
Keep the sorting fast. If the team can't agree on an item quickly, I'd put it in the reserve for this sprint and look at it again at the next refinement.
There's a middle case: work you've chosen to do but can't size yet, like finding out why a service keeps timing out. That's uncertain planned work, so it fits better as a spike with a fixed timebox than as reserve time. You set the spike's limit up front, while the reserve absorbs whatever arrives.
Recurring support duties are a judgment call. If someone handles a weekly patching task or a release check with a known shape, your team can choose to treat it as a planned, sized story. That's our recommendation and your team's call, and the sources above don't cover it. It comes down to whether you know the scope before the sprint starts.
Some items mix both kinds of work, so split them. The urgent fix for a broken export goes to the reserve, and the follow-up work to stop it breaking again becomes a story you can size for a later sprint.
Run the vote on planned stories only
With the reserve agreed, the facilitator says it out loud before the first card. Three sentences at the start of the session are enough, and they slot into any refinement agenda:
- Name the reserve. We're keeping our agreed reserve free for support this sprint, based on the last three sprints.
- Limit the vote. Today we vote only on the planned stories in this list.
- Park the worries. If support worries come up, we'll note them as a capacity topic and come back to them after the round.
That opening tells everyone what the cards measure. Reserve items and interrupt guesses stay off the story list. For the round itself, TinyTroop is free online planning poker: the facilitator opens a room and shares one link, people join with just a display name, and votes stay secret until the cards flip at the reveal.
But someone will still say "support might eat this." Treat it as a capacity topic: note it on the parking list, thank them, and ask for a vote on the size of the work itself. If the worry comes back story after story, your reserve might be too small, and that's a conversation for the end of the session.
If the reveal shows a split and the reason turns out to be interrupt worry, deal with that first. Restate what the reserve covers, then decide what to do after the reveal: re-vote, split the story or park it.
Handle interrupts mid-sprint without breaking the plan
Small interrupts that fit the reserve just get picked up. Anything bigger needs a short conversation. In Scrum, the Product Owner decides whether new work belongs in the Product Backlog and whether it's worth pulling into the current sprint, and the Developers decide whether they can take it on without putting the Sprint Goal at risk.
Scrum.org says that when the Product Owner asks to add work mid-sprint, the Developers may refuse, or negotiate over which work to remove to make room. A swap rule makes that negotiation quick: any new item that isn't reserve work has to name the planned item it replaces. "Can you squeeze this in?" turns into a choice between two named pieces of work.
How you work day to day decides how well you absorb interrupts. When something lands, finish the item you're on before switching if the urgency allows, because half-done work piles up fast. Iqbal writes, "If the team is facing a lot of unplanned work, it is even more pressing for us to limit our work in progress." With fewer items in flight, there's less to put down when the pager goes off.
Put reserve work on your board as it comes in, too, so the retrospective has something to count.
Review the reserve and run your next round
At the retrospective, ask one question: did the reserve cover the interrupts, or was it too much or too little? If it ran out halfway, raise it next sprint. If the team had slack left over, trim it, or keep it and pull the next story forward. Either way, you adjust the reserve and leave past estimates alone.
The reserve is a team agreement about capacity, and the vote sizes the planned stories. Keep them apart, and when support starts leaking into the cards again, revisit the reserve before you touch a single estimate.
Your next planning session can open with one sentence about the reserve and a story list that holds only planned work. Start a free room and try the routine with your team.