# How to Estimate a Data Migration Story in Planning Poker
- URL: https://tinytroop.estacouveflor.com/blog/estimate-data-migration-story-planning-poker/
- Published: 2026-11-24T08:00:00.000Z
- Updated: 2026-11-24T08:00:00.000Z
- Description: List the migration pieces and agree the scope first, so a 3 and a 13 stop meaning different work.
- Author: Cleiton Loiola
- Tags: Estimation, Planning, Team practices, Agile, #run-2026-11-24

Your team brings a story into refinement that says "Migrate customer records to the new database." It sounds like one job. The cards flip, and there's a `3`, a `5` and a `13` on the table, followed by a few minutes of people defending their numbers.

Nobody's wrong if you estimate data migration story planning poker. The `3` and the `13` are estimates for different pieces of work. One person pictured a copy script. Another pictured the copy, the checks afterwards, the switch to the new system and a way back if the switch goes badly.

You can sort most of that out before anyone votes. List the migration pieces, agree which ones belong in this story, vote, and then hear the lowest and highest voters first. It adds a few minutes and saves a lot of going in circles.

## Why migration stories split the vote

When a migration story splits the vote, start by assuming **people pictured different work**. As [Mountain Goat Software's planning poker guide](https://www.mountaingoatsoftware.com/agile/story-points/planning-poker?ref=tinytroop.estacouveflor.com) says, *"The difference between a three and a thirteen is not a math problem. It is a signal that the team is seeing different work."*

Migration stories hide work well because the visible part is small. "Move the rows from A to B" fits on a sticky note. The parts that prove the move worked, and the parts that let you undo it, often never make it onto the card.

[RiteNRG's article on migration architecture](https://ritenrg.com/insights/data-migration-architecture?ref=tinytroop.estacouveflor.com) says, *"A migration can copy every row and still break the business."* A finished copy job is only the start. If the story's done when the script exits, it's small. If it's done when the business trusts the data in the new system, it's a lot bigger. And the card doesn't say which one the product owner meant.

Who sees the extra work depends on who's voting. The **Mountain Goat** guide says, *"A database specialist can reveal hidden migration work. The cards make those differences visible."* Someone who's run a migration before tends to count the pieces that bit them last time, while someone who's only read the ticket counts what the ticket mentions.

Take a typical split. One developer votes `3` because they picture a one-table copy with a script they've written before. Another votes `13` because they're also counting validation and a rollback plan. Both votes are honest, but they're for two different stories, and you can't settle whether `3` or `13` is right until the team agrees which story it's estimating.

## List the migration pieces before anyone votes

The fastest way to stop counting different work is to write the work down. Before the first card, put the pieces of a migration on the story so everyone estimates from the same list.

RiteNRG's breakdown has more detail than a story card needs: "The design needs named layers: discovery, mapping, staging, transformation, loading, validation, cutover, and rollback". For refinement, five pieces cover the parts people tend to argue about:

- Mapping: which source fields go where, and what happens to the ones that don't fit the new shape.
- Dry run: a rehearsal of the move against a copy of the data, before the real one.
- Validation checks: proof that the data arrived whole and still means what it meant.
- Cutover: the switch from the old system to the new one, including any outage window.
- Rollback: how you get back to the old system if cutover goes wrong.

The dry run isn't on RiteNRG's list. It's here because a rehearsal takes time, and it's where a mapping mistake shows up while it's still cheap to fix. If your team never rehearses, cross it off. If you always do, somebody has to count it.

Validation is easy to leave out of a low vote because it happens after the part everyone pictures. [Migravion's migration testing guide](https://migravion.com/blog/data-migration-testing-guide?ref=tinytroop.estacouveflor.com) describes the work as "the structured process of verifying that data has been successfully transferred from a source system". By its definition of completeness, every source record exists in the target after the move. It also says to check that *"no records were skipped, duplicated, or incorrectly filtered out."*

Counts are only part of it. You'll also want to know that links between records survive the move and that values keep their meaning after any format change. Those are usually called integrity and accuracy checks, and each one is work someone has to write and run.

Then decide what this story owns. Before your next migration story, write the five pieces on the card and **mark each one in, out or assumed**, in under two minutes. In means this story does it. Out means it's a separate story, and assumed means someone else handles it or it already exists, so you write down who or what.

Most of the useful conversation happens during the marking. If one person marks rollback as in and another marks it as out, you've found your `3`\-versus-`13` split before anyone played a card. It's the same habit as [naming hidden work before the cards flip](https://tinytroop.estacouveflor.com/blog/estimate-regulated-work-planning-poker-risk/) on regulated stories: the invisible parts get a line on the card, so the vote can count them.

If almost everything ends up marked in and the story still has to fit in one sprint, that's your cue to split it. [Splitting a large story before estimation](https://tinytroop.estacouveflor.com/blog/split-large-user-story-before-estimation/) is cheaper than arguing over a 20\. One split follows the list itself: a story for mapping, a dry run and count checks, then a second story for cutover and rollback.

## Agree scope, then estimate data migration story planning poker

Once the list shows what migration work exists, you still have to decide what this story covers and what done means for it. In Mountain Goat's planning poker flow, this happens before anyone picks a card: *"The team clarifies assumptions and what must be true for the item to be considered complete."*

For a migration story, complete needs an answer for each piece. Is mapping done when a document exists, or when the person who owns the source data has reviewed it? Are checks done when row counts match, or only once the integrity checks pass too? Does the dry run need to be clean, or is one run with a list of known issues enough?

The product owner usually has an opinion on those questions. Better to hear it now than after the reveal, when people have already committed to a number.

The biggest assumption to settle is the cutover pattern, because it changes how big the rollback piece is. **RiteNRG** says, *"Big-bang is a reasonable choice for a small dataset that changes little and can fit safely inside an approved outage."* It also says, "Incremental waves limit the blast radius by moving domains, regions, or cohorts separately."

Those two choices make different stories. With one big move, rollback means getting the whole system back to where it started. With waves, each rollback covers one wave, but you'll probably run cutover more than once. If half the team pictures a big-bang weekend and the other half pictures waves, you'll get a split before anyone's thought about effort, so **pick one as the working assumption** and write it on the card.

If rollback is the part that worries people, [name the rollback risk before your team votes](https://tinytroop.estacouveflor.com/blog/agile-software-risk-estimation-name-risk-before-vote/). Once a risk has been said out loud, everyone can weigh it.

> Left in one person's head, it turns into a silent 13.

Then read the scope line aloud. Something like: "This story covers mapping, one dry run and count checks; cutover and rollback are a separate story." Once everyone's heard it, each person picks a card privately, and the cards stay hidden until everyone reveals together. Secret cards count for more after a scope talk, because whoever talked most about scope can easily anchor the number too.

## Hear the lowest and highest voters first

Agreeing the scope narrows the split, but it won't always close it. When the cards still spread, the spread is telling you something about the work.

Start with the extremes. **Mountain Goat** says, *"The high estimate often reveals hidden work, risk, uncertainty, or complexity."* Ask the highest voter which piece they counted that the scope line didn't mention. On a migration story, it might be a validation check nobody listed, or a cutover step that needs someone outside the team.

Then ask the lowest voter which piece they left out, or what shortcut they see. A low vote can point to a simpler path, like an existing script or a table that turns out to be tiny. Sometimes the low voter is right and the scope shrinks. Sometimes they just hadn't counted rollback.

Update the five-piece list with whatever comes out and **re-vote once**. I wouldn't go past that. Don't average either: if one person says `5` and another says `13`, calling it an `8` hides the reason they disagreed, and that reason is what you were trying to find.

If the second round lands close together, take it. If it's still wide, you're probably missing a fact, and another vote won't produce it.

TinyTroop is a free online planning poker tool where votes stay secret until the reveal, and when they split, it names the outlier votes so your team knows whom to hear first. For a fuller routine after a wide split, read [how to hear the outliers without derailing refinement](https://tinytroop.estacouveflor.com/blog/planning-poker-split-votes-outliers/).

## Record the result and move on

Write the scope next to the number. A `5` on its own tells nobody next sprint what was included, and migration stories are where that question tends to come back. A two-line note is enough: "Scope: mapping, dry run, checks. Assumption: rollback is a separate story." If you agreed a cutover pattern, add that too.

Sometimes the round stalls because nobody knows something basic, like how many records there are or whether the target schema is final. **Mountain Goat's** guide says, *"If the item cannot be estimated because too much is unknown, record the question that needs answering."* Write the question on the story and give it an owner, then decide whether a short spike or a split will get you the answer faster than another vote.

But an unknown doesn't have to block the whole story. You can often estimate the pieces you understand, such as mapping and checks, and park cutover and rollback as their own story until the question's answered.

A migration story gets one honest number when everyone votes on the same pieces, and that only happens if you list them and agree the scope before the cards flip.

On the next migration story in your backlog, put the five pieces on the card and read the scope line aloud before you play the round with your team. [Start a free room](https://tinytroop.estacouveflor.com/new?utm%5Fsource=blog&utm%5Fmedium=cta&utm%5Fcampaign=estimate-data-migration-story-planning-poker), and if someone votes 1 for a cutover, there's a tomato with their name on it.